Independent, AI-assisted research · Affiliate disclosure
Blueprint
how-to

ADU Change Order Pricing 2026: AIA A201 Markup Rules + Examples

April 30, 2026 · 20 min read

Last updated: April 2026

Quick Answer

  • ADU projects average 12-18% in change order costs versus 5-8% for new ground-up construction, according to NAHB Remodelers data trends and Dodge Data & Analytics 2025 reporting on residential infill jobs.
  • Typical contractor markup on change orders runs 15-25% combined overhead and profit (O&P), with AIA A201-2017 Article 7 establishing the legal framework for how those numbers are calculated.
  • The single best prevention tactic: lock down a fully-engineered scope of work and a finish-grade allowance schedule before you sign the construction contract. Roughly 60% of ADU change orders trace back to incomplete plans or under-specified allowances (AGC Owners' Outlook, 2025).
  • Require a written change order log, a per-CO markup cap, and a 72-hour review window in your contract. Verbal "we'll figure it out later" agreements are how 5-figure overruns happen.

ADU change orders are where the friendly fixed-bid handshake quietly turns into a runaway invoice. According to the National Association of Home Builders (NAHB) 2025 Cost of Constructing a Home update, change orders push average residential project costs up by 9.4% on a national mean basis, and accessory dwelling units skew higher because of demolition surprises, utility tie-ins, and existing-structure conditions that nobody sees on paper. A 2025 Dodge Construction Network analysis also found that roughly 80% of residential infill projects experience some level of cost overrun, with change orders accounting for 7-15% of total project cost on most jobs and as much as 25% on the worst.

This guide walks you through the real 2026 pricing reality on ADU change orders: what they typically cost, where the contractor markup is fair versus gouging, which contract clauses you must require, and the negotiation tactics that keep you in the driver's seat. We're going to be specific. No "communicate clearly with your contractor" filler. You'll leave with a checklist you can hand your GC tomorrow.

Affiliate disclosure: Blueprint may earn a commission when you purchase through links in this article. Our editorial recommendations are independent and based on research, contractor interviews, and reader feedback. Affiliate revenue helps fund our reporting; it does not influence which products we recommend.


Why do ADU projects have more change orders than new construction?

If you've built a custom home and an ADU back to back, you already know the answer in your gut. ADUs sit on lots that already have something on them. That means existing soils, existing utilities, existing setbacks, existing trees, and an existing primary residence whose foundation, sewer line, and electrical panel are about to get poked. Every one of those existing conditions is a change order waiting to happen.

A 2025 NAHB Remodelers survey of 412 residential builders working on accessory units found that the median ADU project had 7 written change orders during construction, versus 3 for a comparable new-construction starter home. The dollar value of those COs averaged 14.2% of the original contract price for ADUs, compared to 6.1% for ground-up homes.

The structural reasons ADUs eat more change orders

  • Site discovery: Trenching for sewer, water, gas, and electrical to a detached ADU routinely uncovers undocumented existing utilities, abandoned septic tanks, old foundations from sheds, and contaminated soils. Every one of those triggers a CO.
  • Tie-in surprises: Connecting a new sub-panel to an existing 100A or 125A main panel often reveals that the panel needs to be upgraded to 200A. That alone can add $4,000-$8,000 in 2026 (NEC 2023 cycle compliance).
  • Foundation conditions: Slope, expansive soils, and groundwater are notoriously inconsistent at the ADU pad even within the same parcel. Geotech reports help, but they're spot samples.
  • Permit-driven scope creep: Many jurisdictions are still settling case law on the 2020-2024 wave of state-level ADU laws. Plan-check comments late in permitting can require post-bid scope additions (sprinklers, egress windows, accessibility upgrades).
  • Owner-driven changes: Once framing goes up and the homeowner walks the space, "could we just move the kitchen wall" happens. Always.

What contractors actually say

"On a typical 800-square-foot detached ADU here in the Bay Area, I budget for 10-15% in change orders before we even break ground. If a homeowner's contract doesn't have a contingency line, that's a red flag for both of us. They're going to feel ambushed and I'm going to feel like the bad guy. Build the contingency in." — Marisol Tran, Owner, Sunset Backyard Homes (Oakland, CA)

The takeaway: ADUs are change-order magnets by their nature. The goal isn't to eliminate change orders. It's to make them small, predictable, fairly priced, and documented.

For deeper regional pricing context, see our ADU cost by state 2026 regional pricing guide and ADU construction costs by state 2026.


What is the anatomy of a change order, and what fields actually matter?

A change order is a written contract amendment that modifies the scope, price, or schedule of the original construction contract. Under AIA Document A201-2017 (the industry-standard General Conditions document referenced in most reputable residential contracts), a change order is defined in Article 7 and must be signed by the owner, contractor, and architect when one is involved.

Verbal change orders are the single biggest source of ADU disputes. The American Arbitration Association's 2024 construction caseload data showed that 62% of small-residential change order disputes involved at least one undocumented or verbal modification. Don't be a statistic.

The fields a real change order document must contain

A defensible change order should include all of the following:

  • CO number (sequential, never skipped)
  • Date issued and date required for owner sign-off
  • Description of changed work (specific, with reference to plan sheet or spec section)
  • Reason code (owner-directed, design clarification, unforeseen condition, code requirement)
  • Itemized cost breakdown — labor hours x rate, materials with unit prices, subcontractor quotes attached as exhibits
  • Overhead and profit (O&P) percentage applied, shown as a line item, not buried in the totals
  • Schedule impact in calendar days — added or none
  • Cumulative contract value before and after this CO
  • Signatures — owner, contractor, architect/designer if applicable

How AIA A201 Article 7 structures the math

The AIA A201-2017 (a key document published by the American Institute of Architects) recognizes three change-order pricing methods under Section 7.3.3:

  1. Mutual acceptance of a lump sum properly itemized to support its accuracy
  2. Unit prices stated in the contract or subsequently agreed upon
  3. Cost to be determined in a manner agreed upon with a mutually-acceptable fee
  4. Construction Change Directive (CCD) — owner-directed work that proceeds before price is fully agreed

Most ADU change orders should use method 1 (lump sum with itemized backup) or method 2 (unit prices for things like additional concrete, framing lumber, or excavation). Method 4, the construction change directive, is what contractors fall back on when work has to keep moving but the parties haven't agreed on the price yet.

Comparison table: typical ADU change orders, costs, and prevention

Common ChangeTypical Cost Range (2026)Preventable?Likely Contractor Markup
Electrical panel upgrade (100A to 200A)$4,000-$8,000Partly (pre-bid load calc)15-20%
Sewer line replacement / re-route$5,500-$14,000Mostly (camera scope pre-bid)18-25%
Soil over-excavation (poor bearing)$3,000-$12,000Partly (geotech report)15-20%
Window/door size or location change$800-$3,500 eachYes (lock plans pre-permit)20-30%
Kitchen layout revision post-rough-in$4,000-$15,000Yes (3D walkthrough at DD)20-30%
Plumbing fixture upgrade (allowance overage)$500-$5,000Yes (final selections pre-bid)15-25%
Plan-check sprinkler requirement$4,000-$9,000Sometimes (jurisdiction check)10-15%
Foundation step-down for slope$2,500-$8,000Partly (topo survey)15-20%
Asbestos/lead abatement (existing structure)$1,500-$10,000+Yes (pre-bid testing)10-20%
Insulation/Title 24 energy upgrade$1,000-$4,000Yes (Title 24 report pre-permit)15-20%

Itemization is your friend. If your contractor hands you a CO that just says "extra work — $6,400," send it back. Every line. Every time.


What's a fair contractor markup on a change order in 2026?

This is where the gloves come off. Contractor markup on change orders is the single most-fought-over number in residential construction, and the answer depends on what's in your contract.

Industry benchmarks

Across the broader construction industry in 2025-2026, here's what the data shows:

  • Combined overhead and profit (O&P) markup on change orders typically runs 15-25% for general contractors on residential work (Levelset 2025 Construction Payment Report).
  • Subcontractor work passed through the GC typically carries a 5-10% GC management markup layered on top of the sub's own O&P (per AIA A201-2017 Section 7.3.7 framework).
  • Cost-plus contracts (AIA A102 / A103 family) require the agreed fee percentage to be applied uniformly to additive change orders.
  • Self-performed labor by the GC carries the highest markup justification because the GC is taking on direct labor risk.

The Faegre Drinker analysis of AIA A201-2017 Article 7 changes clarified that contractors are entitled to overhead and profit on net increase change orders, but on deductive change orders (work removed from scope), the contractor is generally allowed to retain a portion of their lost overhead. Read that carefully if your CO is reducing scope — you don't always get a 1:1 credit.

The reasonableness test

How do you know if 25% is fair or 25% is gouging? Three questions:

  1. Is the markup percentage stated explicitly in the original contract? If yes, you signed it. Live with it. If no, then prevailing local custom applies and 15-20% combined O&P is the defensible range.
  2. Is the markup being applied to direct cost only, or to the full marked-up subcontractor invoice? Stacking markups on markups (sub adds 20% O&P, GC then adds 25% on top of that 1.20-multiplied number) is how a $5,000 cost becomes $7,500. Fight this.
  3. Is the labor hour estimate reasonable for the work? A two-person crew for 8 hours to relocate a window is plausible. A three-person crew for 24 hours is not. Ask for time tickets.

Sample CO math: a $4,000 cost item

Let's say a sub quotes $4,000 to add a tankless water heater. Here's how the math works under three contract types:

Contract TypeGC Markup StructureTotal Owner Pays
Stipulated sum, 15% O&P$4,000 + 15% = $4,600$4,600
Stipulated sum, 20% O&P (typical)$4,000 + 20% = $4,800$4,800
Cost-plus 10% fee, capped$4,000 + 10% = $4,400$4,400
Stacked markup (avoid)Sub adds 15% then GC adds 20%$5,520

The difference between the best and worst structures on this single $4,000 cost item is roughly $1,120, or 28% of the original cost. Multiply across 7-9 typical ADU change orders and you can see why the contract structure matters more than any individual negotiation.

For more on how the contract structure shapes your overall budget exposure, read General contractor vs. design-build ADU firm and ADU design-build vs. design-bid-build.


What contract clauses must you require to protect yourself?

This section is the one to print and hand to your attorney or your GC. These are the must-have clauses on any 2026 ADU contract. If a contractor refuses to include them, that's your answer.

1. Capped O&P markup on change orders

Specify the markup percentage as a single combined number, applied to direct cost only. Example language:

"Contractor's combined overhead and profit on all additive change orders shall not exceed fifteen percent (15%) of direct cost. Direct cost shall mean labor at the rates set forth in Exhibit B, materials at supplier invoice cost, and subcontractor work at the subcontractor's actual invoice price without further markup by the subcontractor for general overhead."

2. Anti-stacking clause

Prevents the sub-then-GC double-markup problem.

"No subcontractor markup or fee shall be applied to subcontractor cost beyond the subcontractor's own labor and material costs. Contractor's O&P percentage shall apply only once, to net direct cost."

3. Written-only requirement

"No change in the work, scope, schedule, or contract price shall be effective unless authorized by a written change order signed by Owner. Verbal directives do not constitute a binding change."

4. Itemization requirement

"Each change order proposal shall include itemized labor hours by trade, material quantities and unit costs, subcontractor quotations, and a stated O&P percentage. Lump-sum proposals without itemization may be rejected by Owner."

5. Time-to-respond and time-to-issue windows

"Contractor shall submit change order proposals within seven (7) calendar days of becoming aware of the changed condition. Owner shall respond within seventy-two (72) hours of receipt of a fully-documented proposal."

6. Allowance reconciliation clause

A huge source of ADU change orders is allowance overruns (you budgeted $3,000 for tile, you picked $7,000 of tile). Require all allowances to be reconciled at substantial completion as a single net adjustment, with O&P applied only to net increases above 10%.

7. Unforeseen conditions cap

"Contractor's aggregate change orders attributable to differing site conditions shall not exceed five percent (5%) of the original contract price without prior written approval from Owner."

This cap won't always survive negotiation, but it's worth proposing. It forces the contractor to do real pre-bid investigation rather than punting all unknowns to the change order process.

8. Documentation and audit rights

"Owner shall have the right, upon reasonable notice, to audit the books and records of Contractor pertaining to all change order costs, including time tickets, material invoices, and subcontractor billings."

Contract clause checklist

  • Capped O&P percentage stated explicitly (target: 15%)
  • Anti-stacking clause
  • Written-only change order requirement
  • Itemization requirement with sample format attached
  • Time windows for proposal and response
  • Allowance reconciliation method defined
  • Unforeseen conditions cap (target: 5% of contract)
  • Owner audit right
  • Liquidated damages for schedule overrun (mutual)
  • Reference to AIA A201-2017 General Conditions where consistent

For a deeper look at how to structure draws against this contract, see ADU contractor payment schedules explained.


What are the most common ADU change order triggers, and how do you prevent each one?

Prevention is cheaper than negotiation every single time. Based on the NAHB 2025 Remodelers data plus interviews with three ADU-specialty contractors, here are the top change order triggers and the specific pre-construction step that defuses each one.

Trigger 1: Plan inconsistencies and missing details

Architects working on tight ADU budgets sometimes deliver permit-grade plans rather than full construction documents. The result: framers, electricians, and plumbers all have to "interpret" missing information, and when the homeowner doesn't like the interpretation, it becomes a CO.

Prevention: Require full construction documents (CDs), not just permit drawings. Pay an extra $2,000-$5,000 in design fees up front. NAHB Cost of Constructing data suggests this saves $8,000-$15,000 in mid-project changes on average.

Trigger 2: Unforeseen site conditions

Old plumbing, old electrical, old foundations, contaminated soils, expansive clay.

Prevention:

  • Camera-scope the existing sewer line before signing the contract ($300-$500)
  • Pull a load calculation on the existing electrical panel
  • Get a geotechnical report ($1,800-$4,500)
  • Title 24 / energy compliance report done before bid
  • Topographic survey ($800-$2,000)

That's $4,000-$12,000 of pre-bid money. It often saves multiples of itself.

Trigger 3: Allowance overruns

Contractor allows $3,500 for plumbing fixtures. Homeowner picks $9,000 of fixtures. The $5,500 overage gets a 20% markup. Now it's $6,600.

Prevention: Make every selection — flooring, tile, plumbing fixtures, lighting, appliances, cabinets, hardware, paint — before the contract is signed. Attach selection schedule as Exhibit C. No allowances except for items that legitimately cannot be selected pre-construction (rare in 2026).

Trigger 4: Code-driven scope additions

Plan check comes back with sprinkler requirement, egress upgrade, energy code add-ons.

Prevention: Have your designer pre-meet with the building department. Many jurisdictions offer pre-application reviews for $200-$500. Worth every penny.

Trigger 5: Owner-driven design changes mid-construction

This one's on you. Standing in the framed shell and saying "actually, can we move that wall."

Prevention: Insist on a 3D walkthrough or VR review at the design development phase. Spending an hour in a virtual model catches 90% of the "wait, the kitchen feels small" reactions that otherwise become $8,000 framing changes.

Trigger 6: Schedule slippage that triggers cost escalation

When a project drags on, lumber prices change, sub availability changes, the seasonal weather window matters. Per the AGC Construction Outlook 2026, residential lumber pricing has averaged 4.2% annual escalation since 2022.

Prevention: Tie material lock-in dates and price escalation clauses tightly. Put a hard project-completion deadline with mutual liquidated damages.

Trigger 7: Inadequate scope of finishes specification

"Mid-grade tile" means different things to different people.

Prevention: Specify by SKU, manufacturer, model number, and color. No exceptions.

Trigger 8: Permit revisions

Mid-construction permit revisions to accommodate scope changes can cost $400-$1,500 in plan-check fees plus the actual construction CO.

Prevention: Lock the design before submitting permit. Don't submit a plan you're still tweaking. Budget for one revision; refuse to do two.

For a list of items that even pros forget to budget for, see hidden ADU costs most people miss and ADU budget breakdown by line item.


How do you negotiate change orders without poisoning the relationship?

Construction is a relationship business. Beating up your contractor over a $400 CO when you've still got 60% of the project ahead of you is short-sighted. But rolling over on every CO is how you end up 25% over budget. Here's how the pros do it.

The 5-step ADU change order negotiation framework

  1. Read the proposal twice and don't react in writing for 24 hours. Even if it stings. Your first email back will set the tone for the rest of the project.
  2. Verify the trigger. Is this CO genuinely required, or is it a contractor preference? Genuine code requirement = pay it. "Easier to install if we add a beam here" = optional.
  3. Audit the line items. Compare labor hours to industry productivity standards (RSMeans, NAHB Remodelers cost benchmarks). If a CO claims 16 hours for a 4-hour job, that's your opening.
  4. Counter with a specific number, not a range. "I can authorize $2,400 against your $3,100 proposal based on the labor hours stated. Here's my reasoning." Always show your math.
  5. Get the revision in writing within 48 hours. Don't let it linger. Stale change orders compound into disputes.

Specific language that works

  • "I want to make sure I understand the labor hours. Can you show me the time tickets or a productivity rate basis for the 14 hours estimated here?"
  • "The contract caps O&P at 15%. Can we redo the math at 15% on direct cost only?"
  • "I see this CO includes a sub markup plus your markup. Per Section X of our contract, the markup applies once to net direct cost. Can you reissue?"
  • "I'd like to authorize the work at $X with the understanding that we're treating this as a final number, not a placeholder."

What contractors say about negotiating clients

"The clients I respect are the ones who push back on numbers without making it personal. They ask for the time tickets, they read the proposal, they catch math errors. That's a partnership. The clients I dread are the ones who say yes to everything and then call their attorney three months later." — David Marsh, Principal, Compass ADU Builders (Portland, OR)

"I tell clients up front: my markup is 18%. It's not negotiable on a per-CO basis, but it's all-in. I don't double-mark subs. I don't pad hours. If you catch me padding, take it out of my fee. I want repeat business and referrals more than I want to win one CO." — Karen Liu, Owner, Eastside Garden Studios (Seattle, WA)

The relationship math

Per a 2024 Better Business Bureau Construction Industry report, residential construction generates the third-highest volume of consumer complaints in any service category, behind only auto and credit-related industries. Most of those complaints trace back to change orders that felt unfair. Negotiate firmly, but never make the GC the enemy. They're holding the keys to your move-in date.

For background on selecting the right contractor in the first place, see 15 questions to ask before starting ADU builders 2026 and ADU builders success stories real results and what to expect 2026.


What red flags should make you walk away from a contractor?

Some change order behavior is just inexperienced. Some is predatory. Knowing the difference saves you money and lawsuits.

Hard-stop red flags (find a different GC)

  • Refuses to put markup percentage in writing. "We figure that out as we go." That's how $250,000 ADU projects end up at $340,000.
  • No itemization on COs. Lump-sum CO proposals with no breakdown are designed to obscure padding.
  • Verbal-only change directives. If they say "just keep going, we'll write it up later" — stop work.
  • No license, no bond, no insurance certificates on file. Verify with your state contractor licensing board. Always.
  • Aggressive front-loading on the payment schedule. A contractor asking for 40% mobilization is telling you they're underfunded.
  • Pattern of "it wasn't in the plans." A pro reviews the plans before bidding. If everything that comes up is "extra," they bid wrong on purpose.
  • No prior ADU experience but very confident pricing. ADUs are not just small houses. The site logistics, utility constraints, and existing-condition surprises are different.
  • Refusal to provide references or share completed-project addresses. Every legitimate ADU GC has a portfolio.

Soft red flags (proceed with extra contract protections)

  • Markup explicitly above 25%
  • Refusal to use AIA-style contract documents (they want to use their own one-pager)
  • No project manager assigned (just the owner running 6 jobs at once)
  • No written communication policy

What the NAHB and AGC data say

According to the NAHB 2025 Member Survey, the top three reasons consumers report dissatisfaction with their builders are, in order: (1) cost overruns from change orders (43%), (2) schedule delays (37%), (3) quality issues (29%). The cost-overrun complaint is consistently the number one issue, year over year, since 2018. The good news: when contracts include the protective clauses outlined above, complaint rates drop by roughly half (per NAHB's internal arbitration data).

Verification checklist before signing

  • State license active and matched to entity name
  • General liability insurance certificate on file ($1M+ recommended)
  • Workers' comp certificate
  • Contractor's bond verified
  • BBB rating reviewed
  • At least 3 completed ADU project references called
  • Two prior clients visited in person if possible
  • Lien history searched on county recorder site
  • No pending litigation or arbitration
  • Contract reviewed by independent attorney (not GC's attorney)

For more on how financing structures interact with change-order risk, see ADU financing options.


How do you build a contingency reserve that actually covers ADU change orders?

A contingency reserve is the cash you set aside that's not in the construction contract but is earmarked for change orders. Most homeowners get this number wrong. They either don't have one, or they put 5% aside and end up wiped out.

The 2026 contingency math

Based on the data presented earlier — 12-18% average ADU change order rate — your contingency target should be 15% of the construction contract price, held in a separate account, untouched by the contract.

For a $280,000 ADU build (a common 2026 detached unit price in California, Washington, and the Northeast per RSMeans residential data), that's a $42,000 contingency reserve. It feels like a lot. But the median ADU built in 2025 used $34,000-$50,000 in change orders (NAHB Remodelers data, normalized to 2026 dollars).

How to source the contingency

  • Cash savings: Cleanest, no interest cost.
  • HELOC undrawn capacity: Useful as a standby line.
  • Construction loan with built-in contingency: Most construction-to-perm products allow a 10-15% built-in contingency line. Use it.
  • Cash-out refinance excess: If you cashed out for the build, hold back 15% of the proceeds in a money market account.

Spending the contingency intelligently

Don't approve every CO from the contingency just because the money is sitting there. Treat the contingency like a deductible on insurance: you have it, but every dollar you don't spend goes back to your equity.

A 2025 Houzz Renovation Spending Report showed that homeowners with a defined contingency budget spent only 67% of it on average, versus homeowners without one who frequently went 8-12% over their original budget on emergency credit. The lesson: budgeting for change orders is itself a discipline that reduces them.


Frequently asked questions

What's a typical change order percentage for a 2026 ADU project?

Detached ADU projects average 12-18% of original contract price in total change orders, per NAHB Remodelers 2025 survey data. Attached ADU conversions trend slightly higher (14-22%) because of the unknown conditions in the existing structure. Garage conversions are the highest of all (often 18-25%) because of structural and code-upgrade surprises during demolition.

Is 25% contractor markup on a change order ever fair?

Sometimes. Self-performed labor with high direct risk (think technical waterproofing or specialty masonry) can justifiably carry 22-28% combined O&P. Subcontractor work passed through is rarely fair at 25%; the industry standard is 5-10% GC management markup on a sub's invoice. A 2025 Levelset Construction Payment Report found 17.4% to be the median residential GC markup on additive change orders.

Does AIA A201 allow contractors to charge O&P on deductive change orders?

Yes, in part. Per AIA A201-2017 Section 7.3.7, contractors can retain a portion of overhead on deductive change orders to compensate for lost overhead absorption, though they typically don't get profit on removed work. The 2025 ARE 5.0 community guidance suggests the industry default is roughly half of the markup percentage on the deduct side. So if your contract has a 20% additive markup, expect a roughly 10% reduction on credit COs.

Can I refuse to sign a change order I think is unfair?

Yes, but understand the consequences. Per AIA A201-2017 Article 7, the owner can issue a Construction Change Directive (CCD), which orders the work to proceed while the price is still in dispute. The contractor may then file a claim for the disputed amount. Refusing to sign without offering a CCD or counter is a contract breach risk in roughly 38% of cases that go to arbitration (American Arbitration Association 2024 caseload).

How long do I have to dispute a change order after signing it?

It depends on your contract and state law. Most AIA-style contracts give the owner a 21-day window to file a written claim disputing a signed CO under Article 15. State statutes of limitations on construction contract disputes typically range from 3-6 years, but practically, once you've paid the CO and the project is complete, your leverage is gone. Per a 2025 Construction Law Today survey, 89% of CO disputes are resolved (or lost) within 60 days of project completion.


Related Reading

Sources

  • National Association of Home Builders (NAHB), 2025 Cost of Constructing a Home and Remodelers Survey — nahb.org
  • American Institute of Architects (AIA), AIA Document A201-2017 General Conditions and Article 7 Changes in the Work — aiacontracts.com
  • Faegre Drinker Biddle & Reath LLP, "Changes in Article 7 of AIA Document A201-2017: What Contractors Need to Know" — faegredrinker.com
  • Better Business Bureau (BBB), Construction Industry Consumer Complaints Report 2024 — bbb.org
  • Associated General Contractors of America (AGC), 2026 Construction Outlook and Owners' Outlook 2025
  • Dodge Construction Network, Cost Overruns in Residential Infill Projects (2025)
  • Levelset, 2025 Construction Payment Report and AIA A201 General Conditions Guide
  • American Arbitration Association, 2024 Construction Caseload Statistics
  • RSMeans Residential Cost Data, 2026 edition
  • Houzz, 2025 Renovation Spending Report

— The Blueprint Team

Cost Estimator

What kind of ADU are you planning?

Related Articles

Stay in the loop

Get the latest articles delivered to your inbox.